Project Description
The El Jobean MSBU was approved in November 2018. This project includes construction of a wastewater collection system to service approximately 300 properties with sewer service, a booster pump station to increase potable water pressure to West County at the Myakka River and a vacuum station that will provide sewer collection for the wastewater system. Construction on the booster pump and vacuum station is completed, and a ribbon-cutting was held on Nov. 16. Construction of the wastewater system is expected to be completed by fall 2021. Plumbing connections to the wastewater system are expected to be completed by summer 2022.
- Phase 4 connections have begun. You will receive a door hanger approximately a week prior to connection of your home.
- Contractor: Milorad Pudja Plumbing LLC
- Phase 3 connections are complete.
- Contractor: Milorad Pudja Plumbing LLC
- Project surveys have been sent out to residents in the project area.
- Phase 2 connections are complete.
- Contractor: Rohaley and Sons Plumbing Contractors, Inc.
- Phase 1 connections are underway.
- Contractor: Liberty R and V Construction, Inc.
- Vacuum Station construction complete
- Update 4/14/20: The BCC approved the contract for the El Jobean Vacuum Sewer System. Contractor: Guymann Construction of Florida, Inc. Estimated completion: Fall 2021
For an Installation Agreement and Septic Location Form, please contact the Capital Projects Office at 941.764.4305 or at S2S@CharlotteCountyFL.gov
Capital Projects Office
Phone: 941.764.4305
Email: S2S@CharlotteCountyFL.gov
Project Location
El Jobean East- Watchchou Ave. to River Beach Drive.
Construction will also occur along Railroad Avenue.
Latest Updates
Construction of the wastewater system is nearing completion.
Phases 2 and 3 connections are complete. Phases 1 and 4 connections are underway and should be completed by June 2022.
Budget
Phase | Cost |
---|---|
Construction | $5,342,181 |
Resident Assessments, Florida Department of Environmental Protection State Revolving Funds and EPA Grants
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 05/01/2020 | 06/30/2022 | |
Turnover & Closeout | 05/01/2021 | 07/29/2022 |
Supporting Materials

Project Phase
Construction
Last Updated
06/07/2022
Project Manager
Dean Campbell
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Design Engineer/Architect
Giffels-Webster Engineers
Construction Contractor
Guymann Construction of Florida, Inc.