Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

El Jobean East Wastewater Expansion

Project Description

The El Jobean MSBU was approved in November 2018. This project includes construction of a wastewater collection system to service approximately 300 properties with sewer service, a booster pump station to increase potable water pressure to West County at the Myakka River and a vacuum station that will provide sewer collection for the wastewater system. Construction on the booster pump and vacuum station is completed, and a ribbon-cutting was held on Nov. 16. Construction of the wastewater system is expected to be completed by fall 2021. Plumbing connections to the wastewater system are expected to be completed by summer 2022.

Project Updates
  • Phase 4 connections have begun. You will receive a door hanger approximately a week prior to connection of your home.
    • Contractor: Milorad Pudja Plumbing LLC 
  • Phase 3 connections are complete.
    • Contractor: Milorad Pudja Plumbing LLC
  • Project surveys have been sent out to residents in the project area. 
  • Phase 2 connections are complete.  
    • Contractor: Rohaley and Sons Plumbing Contractors, Inc.
  • Phase 1 connections are underway. 
    • Contractor: Liberty R and V Construction, Inc.
  • Vacuum Station construction complete
  • Update 4/14/20: The BCC approved the contract for the El Jobean Vacuum Sewer System. Contractor: Guymann Construction of Florida, Inc. Estimated completion: Fall 2021

For an Installation Agreement and Septic Location Form, please contact the Capital Projects Office at 941.764.4305 or at S2S@CharlotteCountyFL.gov

Capital Projects Office
Phone: 941.764.4305
Email: S2S@CharlotteCountyFL.gov

Project Location

El Jobean East- Watchchou Ave. to River Beach Drive. 

Construction will also occur along Railroad Avenue.

Latest Updates

Construction of the wastewater system is nearing completion.

Phases 2 and 3 connections are complete. Phases 1 and 4 connections are underway and should be completed by June 2022.

Budget

Phase Cost
Construction $5,342,181
Funding source(s):

Resident Assessments, Florida Department of Environmental Protection State Revolving Funds and EPA Grants

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Construction 05/01/2020 06/30/2022
Turnover & Closeout 05/01/2021 07/29/2022

Supporting Materials

El Jobean East Wastewater Expansion Project Image

Project Phase
Construction

Last Updated
06/07/2022

Project Manager
Dean Campbell

Public Relations
Caroline Wannall
Email Public Relations

Sponsor Department
Utilities

Design Engineer/Architect
Giffels-Webster Engineers

Construction Contractor
Guymann Construction of Florida, Inc.

Delivering Exceptional Service

Questions? Issues?

Contact Us