Project Description
Replacement and improvement of playground equipment and shade structure that was damaged during Hurricane Ian along with the installation of an additional pavilion and drinking fountain for community use.
Project Location
Englewood East Park
11120 Sunnydale Ave
Englewood, FL 34224
Latest Updates
Construction permits have been submitted and construction is scheduled to begin June 15, 2026.
Installation is ahead of schedule and will begin the week of June 8, 2026.
Installation is complete and waiting on final permit inspections.
Budget
| Phase | Cost |
|---|---|
| Design | $235,296.70 |
| Construction | $176,994.93 |
| Total Budget | $412,291.63 |
CMP-Master Planning
Hurricane Recovery
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 08/01/2026 | 08/31/2026 | 07/28/2026 |
| Turnover & Closeout | 09/01/2026 | 09/30/2026 |
Supporting Materials
Project Phase
Completed
Sponsor Department
Community Services
Design Engineer/Architect
DMK Associates, Inc.
Construction Contractor
Rep Services, Inc.