Project Description
Design a new scalable fire station to replace the existing station. The new Fire Station 2 will be located on Collingswood in the Murdock Village area.Project Impacts
.Latest Updates
Punchlist walkthrough was conducted with Engineer, Architect, General Contractor, and Facilities Projects Manager.
Budget
Phase | Cost |
---|---|
Design | $494,946.00 |
Construction | $5,459,982.00 |
Total Budget | $6,500,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 02/18/2019 | 05/31/2019 | 04/19/2019 |
Design Development | 09/24/2019 | 12/31/2020 | |
Construction | 03/15/2021 | 04/29/2022 |
Project Phase
Construction
Last Updated
05/13/2022
Project Manager
Pedro Agosto
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Public Safety
Design Engineer/Architect
Wilder Architecture, Inc
Construction Contractor
Wharton-Smith, Inc