Fire Station 3 is located at (US 776) El Jobean Road and Newcomb Road. It was built in 1977 and is at the end of the life cycle of the building. The present building is undersized and does not meet the current and future needs including,

  • not hardened for hurricane resistance
  • lack of capacity for storage, equipment, apparatus and supplies.
  • inadequate personnel capacity and kitchen facilities.

Project Location

4322 El Jobean Rd, Port Charlotte< FL 33953

Project Impacts

Weather

ACOE (Army Corps of Engineers)

Latest Updates

The new Fire Station 3 will be located on the existing site at 4322 El Jobean Rd. The CM@Risk submitted a Guaranteed Maximum Price estimate on 1/14, which is currently under review.

Budget

Phase Cost
Design $496,986.66
Construction $4,334,000.00
Other Costs $300,000.00
Total Budget $4,834,000.00
Funding source(s): 2020 Sales Tax

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 11/16/2023 02/27/2024 01/17/2025
Design Development 03/03/2025 08/29/2025 01/14/2026
Construction 05/16/2026 05/16/2027
Turnover & Closeout 03/02/2027 04/02/2027

Project Phase
Design Development

Last Updated
01/28/2026

Project Manager
Joe Romanelli

Public Relations
Ashley Turner
Email Public Relations

Project Number
c222103

Sponsor Department
Public Safety Charlotte County Fire and EMS

Design Engineer/Architect
Schenkel Shultz

Construction Contractor
Wharton-Smith/Jon F. Swift

Sales Tax Project

Delivering Exceptional Service

Questions? Issues?

Contact Us