Project Description
Project will replace the existing two-lane Flamingo Boulevard from 776 to a point north of Edgewater Drive and the existing remaining section of two-lane Edgewater Drive from Midway Boulevard to Collingswood Boulevard with a new four-lane roadway. The project will also connect Flamingo Boulevard from its southernmost curve to the intersection of Edgewater Drive and Collingswood Boulevard, creating a new alignment for the roadways. Additionally, intersection improvements at 776 and Flamingo Boulevard will be included.
The project is split into 3 phases, identified as phases 3, 4, & 5. The design will include all three phases and the construction will be multiphase.
Project Location
Flamingo Boulevard from 776 to a point north of Edgewater Drive, connecting Flamingo Boulevard from its southernmost curve to the intersection of Edgewater Drive and Collingswood Boulevard, including Edgewater Drive from Midway Boulevard to Collingswood Boulevard.
Latest Updates
Johnson Engineering has been selected as the design firm for this project. The county is working with the firm to design all project phases.
- 100% plans received for all phases and under review and comment phase. Final plan adjustment will be made before signed and sealed construction plans are received early next year.
- Voluntary property acquisition in progress near completion and will be advancing to the eminent domain process upon final plan completion.
- SWFWMD permit approved and in place for these projects.
- Coordination to resolve outside utility conflicts is ongoing. Engineer of record is renewing Sunshine one call and will be working on obtaining new and final utility work agreements from private utility owners, prior to the construction bid phase.
- FDOT Lap project review was recently complete and now bid doc review is in progress for the SR776 intersection work. Once bid doc review is complete a draft bid package will be sent to FDOT for review and approval to advertise for construction bid.
- FDEP permitting for SR776 utility work are now approved and in place for the project. Awaiting FDEP permits for remaining phases.
- ACOE Agency permitting review in progress for phase 3, 4, & 5.
Budget
| Phase | Cost |
|---|---|
| Design | $5,068,415 |
2014 Sales Tax Extension for the design of phases 3, 4, & 5.
2020 Sales Tax Extension for the construction of phase 4, in the future.
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 03/01/2022 | 02/28/2026 | |
| Construction | 03/01/2028 |
Supporting Materials
Project Phase
Design Development
Last Updated
12/02/2025
Project Manager
Zach Patchell
Public Relations
Chad Ray
Email Public Relations
Project Number
c412102
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD


