Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Flamingo/Edgewater Widening

Project Description

Project will replace the existing two-lane Flamingo Boulevard from 776 to a point north of Edgewater Drive and the existing remaining section of two-lane Edgewater Drive from Midway Boulevard to Collingswood Boulevard with a new four-lane roadway. The project will also connect Flamingo Boulevard from its southernmost curve to the intersection of Edgewater Drive and Collingswood Boulevard, creating a new alignment for the roadways. Additionally, intersection improvements at 776 and Flamingo Boulevard will be included. 

The project is split into 3 phases, identified as phases 3, 4, & 5. The design will include all three phases and the construction will be multiphase. 

Project Location

Flamingo Boulevard from 776 to a point north of Edgewater Drive, connecting Flamingo Boulevard from its southernmost curve to the intersection of Edgewater Drive and Collingswood Boulevard, including Edgewater Drive from Midway Boulevard to Collingswood Boulevard. 

Latest Updates

Johnson Engineering has been selected as the design firm for this project. The county is working with the firm to design all project phases. The design and permitting portion is expected to take about two and half years from the notice to proceed date of March 1, 2022.

  • 95% of field survey work has been completed.
  • Protected species and wetlands evalution in process.
  • 95% of geotechnical field work has been completed.
  • 90% roadway and bridge plans for Ph.4 received and staff comments returned to Engineer. Currently working toward final design.
  • 90% roadway and bridge plans for Ph.3 and Ph.5 are under review awaiting Charlotte county staff comments. 
  • 90% utility plans are in progress for Ph.5.
  • 85% Property acquisition in progress.
  • Recently the county obtain the necessary SWFWMD permit.
  • Coordination to resolve outside utility conflicts is ongoing. 
  • FDOT Lap project review is in progress for the SR776 intersection work.
  • Submitted and awaiting SWFWMD permitting for SR776.
  • ACOE Agency permitting review in progress for phase 3, 4, &5.

Budget

Phase Cost
Design $5,068,415
Funding source(s):

2014 Sales Tax Extension for the design of phases 3, 4, & 5.

2020 Sales Tax Extension for the construction of phase 4, in the future.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 03/01/2022 02/28/2025
Flamingo/Edgewater Widening Project Image

Project Phase
Design Development

Last Updated
02/12/2025

Project Manager
Zach Patchell

Public Relations
Tracy Doherty
Email Public Relations

Project Number
c412102

Sponsor Department
Public Works

Design Engineer/Architect
Johnson Engineering

Construction Contractor
TBD

Sales Tax Project

Delivering Exceptional Service

Questions? Issues?

Contact Us