Project Description
Design and construct a sidewalk on Fruitland Avenue and Avenue of the Americas.Project Location
Fruitland Avenue from Winchester Boulevard to Gulfstream Boulevard and Avenue of the Americas from San Casa Drive to Winchester Boulevard.Latest Updates
The contractor has completed the punch list items and fianl acceptance is being issued. The close out paperwork is being done to finish the project.Budget
| Phase | Cost |
|---|---|
| Design | $170,960.30 |
| Construction | $714,000.00 |
| Total Budget | $884,960.30 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 10/01/2021 | 11/30/2021 | 03/22/2022 |
| Design Development | 03/23/2022 | 11/18/2023 | 12/28/2023 |
| Construction | 06/03/2024 | 09/30/2025 | 11/03/2025 |
| Turnover & Closeout | 11/04/2025 | 12/01/2025 |
Project Phase
Turnover & Closeout
Last Updated
12/02/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Caltran Engineering/ SED
Construction Contractor
Marquee Development