Project Description
Design and construct a sidewalk on Fruitland Avenue and Avenue of the Americas.Project Location
Fruitland Avenue from Winchester Boulevard to Gulfstream Boulevard and Avenue of the Americas from San Casa Drive to Winchester Boulevard.Latest Updates
The Avenue of the Americas / Fruitland sidewalk construction has started. The contractor has the Fruitland Ave. section completed and has moved to the Ave. of the Americas section of the project, storm structures and piping has been installed. They are working on installing stabilized base and concrete sidewalk and driveways at this time. Additional work was needed at the Worth Ave./ San Casa Dr. intersection a change order is being issued to address this and additional day will be added to the contract.Budget
Phase | Cost |
---|---|
Design | $170,960.30 |
Construction | $714,000.00 |
Total Budget | $884,960.30 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/01/2021 | 11/30/2021 | 03/22/2022 |
Design Development | 03/23/2022 | 11/18/2023 | 12/28/2023 |
Construction | 06/03/2024 | 02/05/2025 |
Project Phase
Construction
Last Updated
03/13/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD