Project Description
GC Herring Phase I design and construction will include two (2) playgrounds including shade structures, one ages 2-5 and one ages 6-12, one large pavilion and two small pavilions, one tennis court, one basketball court, fitness hub with shade structure, multi-purpose field area and exercise trail.
Project Location
G.C. Herring Park
3406 Indiana Rd.
Placida, Florida 33946
Project Impacts
Protected species mitigation and permits
Inclement weather
Latest Updates
Construction of the shade structure and installation of the fitness hub equipment have been completed. Installation of the playground equipment and sunshades is approximately 95% complete. Site work remains ongoing, with sidewalks and the exercise trail currently being poured.
Budget
| Phase | Cost |
|---|---|
| Design | $249,900 |
| Construction | $3,138,290 |
| Total Budget | $3,388,190.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 11/02/2020 | 10/02/2023 | |
| Design Development | 03/26/2024 | 10/28/2025 | 12/11/2025 |
| Construction | 12/09/2025 | 07/31/2026 | |
| Turnover & Closeout | 07/31/2026 | 09/30/2026 |
Supporting Materials
Project Phase
Construction
Last Updated
05/13/2026
Project Manager
Vicki Chichura
Public Relations
Brian Gleason
Email Public Relations
Project Number
c722105
Sponsor Department
Community Services
Design Engineer/Architect
Kimley-Horn
Construction Contractor
Jon F. Swift Construction