Project Description
Design and construct a pathway on Gasparilla Pines Boulevard
Project Location
Gasparilla Pines Boulevard from Placida Road (CR 775) to the end of road at the Amberjack Environmental Park.Latest Updates
The 100% plans and bid package were received . The approved SWFWMD exemption was received. The MSBU committee has requested to push construction out to FY 26 for funding, The advisory board requested estamates to possabily split the project into phases or shorten the project waiting for direction form the board moving foward.Budget
Phase | Cost |
---|---|
Design | $116,900.00 |
Construction | $611,000.00 |
Total Budget | $727,900.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/03/2022 | 03/01/2023 | 03/01/2023 |
Construction | 01/01/2026 | 07/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
04/14/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD