Project Description
The primary objective of this project entails the construction of a sidewalk extension across Gasparilla Rd, facilitating the connection between the Pioneer Trail and the pre-existing sidewalk situated south of Gasparilla Rd, in close proximity to Gasparilla Marina. In addition, we are planning to install rectangular rapid flash beacons at the designated crosswalk along Gasparilla Rd. The plan includes the replacement of specific segments of asphalt sidewalk on the southern side of Gasparilla Rd with concrete sidewalks. This sidewalk extension will contribute to the overall safety and convenience for pedestrians utilizing this particular section of the sidewalk network.
Project Location
15001 Gasparilla Rd, PlacidaBudget
Phase | Cost |
---|---|
Construction | $200000 |
Total Budget | $79,545.57 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 04/03/2023 | 11/01/2023 | 10/16/2023 |

Project Phase
Planning and Project Approval
Last Updated
10/16/2023
Project Manager
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
In House
Construction Contractor
In-house and ERS