Project Description
The BOCC has requested engineering to design & construct a 6'sidewalk on the West side Gasparilla Rd. (Boca Grande) to improve walkabilityProject Location
Connecting to the existing 6' sidewalk at the South end of the Gasparilla Island Bridge Authority ROW going South to the intersection of Gulf Shores Drive.Latest Updates
-
RWA Engineering was selected as the design consultant for the project.
-
The project survey has been completed.
-
The 30% design plans have been submitted and are currently under staff review.
-
Staff will provide review comments and return the plans to the Engineer of Record to advance the project to the 60% design phase.
Budget
| Phase | Cost |
|---|---|
| Design | $37,250.00 |
| Construction | $250,000.00 |
| Total Budget | $287,250.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 07/16/2025 | 09/23/2025 | |
| Design Development | 10/01/2025 | 07/15/2026 |
Project Phase
Design Development
Last Updated
02/02/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
RWA
Construction Contractor
TBD