Project Description
Gillot Blvd at the Blitman Waterway in the Gulf Cove area has sustained roadway damage and major erosion within the right-of-way. The roadway and right-of-way will need to be reconstructed to include the installation of a new guard rail and water main.Project Location
Gillot Blvd between Richards Ave and Abrams AveProject Impacts
Gillot Blvd is currently closed at this location. A detour for traffic is in place.Latest Updates
Kisinger Campo and Associates has submitted the final plans to the Florida Department of Transportation for final review and approval.
KCA is currently in the final permit process phase with Army Corps of Engineers and US National Fisheries.
Contract documents have been submitted to FDOT for their review.
Budget
Phase | Cost |
---|---|
Design | $56,796 |
Engineering | $68,155 |
Construction | $567,960 |
Total Budget | $692,911 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 02/05/2023 | 10/16/2023 | 02/05/2024 |
Design Development | 03/11/2024 | 06/24/2024 | |
Construction | 01/06/2025 | 03/21/2025 | |
Turnover & Closeout | 03/21/2025 | 04/18/2025 |
Project Phase
Design Development
Last Updated
10/14/2024
Project Manager
Jeff Keyser
Public Relations
Tracy Doherty
Email Public Relations
Project Number
FN453062-1
Sponsor Department
Public Works
Design Engineer/Architect
Kisinger Campo and Associates
Construction Contractor
TBD