Project Description
Gillot Blvd at the Blitman Waterway in the Gulf Cove area has sustained roadway damage and major erosion within the right-of-way. The roadway and right-of-way will need to be reconstructed to include the installation of a new guard rail and water main.Project Location
Gillot Blvd between Richards Ave. and Abrams Ave.Latest Updates
V&H Construction has completed Gillot Boulevard and the roadway is now open to all traffic.
Budget
| Phase | Cost |
|---|---|
| Design | $56,796 |
| Construction | $435,840.30 |
| Total Budget | $492,636.30 |
Florida Department of Transportation grant funding
Charlotte County Internal Funding
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 02/05/2023 | 10/16/2023 | 02/05/2024 |
| Design Development | 03/11/2024 | 06/24/2024 | 12/11/2024 |
| Construction | 07/07/2025 | 09/05/2025 | 08/25/2025 |
| Turnover & Closeout | 08/26/2025 | 09/26/2025 | 09/16/2025 |
Project Phase
Completed 03/02/2026
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
20250166 - FN453062-1
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Kisinger Campo and Associates
Construction Contractor
V & H Construction Inc.


