Project Description
These 3 bridges require design services to implement the FDOT maintenance and repair items for each of the respective bridges.
Bridge #014030 Pellam Boulevard over Auburn Waterway
Bridge #014043 Wintergarden Avenue over Como Waterway
Bridge #014069 O'Hara Drive over Atlantus Waterway
Project Location
Bridge #014030 Pellam Boulevard over Auburn Waterway
Bridge #014043 Wintergarden Avenue over Como Waterway
Bridge #014069 O'Hara Drive over Atlantus Waterway
Latest Updates
Project Activities for April 2025
The County has approved the 60% design plans and will get the 100% design plans and construction bid documents on April 25, 2025.
Budget
Phase | Cost |
---|---|
Design | $189,895 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/16/2024 | 04/18/2025 |
Project Phase
Design Development
Last Updated
04/10/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Kimley-Horn Engineers