Project Description
The Gulf Cove Street and drainage MSBU requested to design & construct 6' sidewalks on the south side of David Boulevard, the south side of Gillot Boulevard, the north side of Foresman Boulevard & the west side of Holton Terrace.Project Location
Design & Construct 6' sidewalks on
- David Boulevard from Holton Terrace to Foresman Boulevard
- Gillot Boulevard from SR 776 to David Boulevard
- Foresman Boulevard from David Boulevard to Holton Terrace
- Holton Terrace from Foresman Boulevard to David Boulevard
Project Impacts
Funding for this project was pushed out to FY26 for phase 1. Gillot Blvd. SR776 to David Blvd.Latest Updates
100% plans for David Boulevard, Gillot Boulevard, Holton Terrace, and Foresman Boulevard were received. Construction was pushed until FY28 to allow for the SunTrail to be completed.Budget
Phase | Cost |
---|---|
Design | $247,913.15 |
Construction | $4,510,000.00 |
Total Budget | $4,757,913.15 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 06/20/2018 | 07/31/2019 | 07/31/2020 |
Construction | 12/15/2025 | 06/15/2026 |
Project Phase
Design Development
Last Updated
03/13/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering / Southwest Engineering
Construction Contractor
TBD