Project Description
This project will install an 8-inch water main along Hillsborough Boulevard from Yorkshire St. to US 41. The water main will be installed parallel to the Peace River Manasota Water Authority’s 42-inch Phase 2B Pipeline.
The Peace River Manasota Water Authority’s Regional Integrated Loop Phase 2B Pipeline is a 42-inch steel potable water transmission main that will start at the Authority's existing 42-inch Regional Interconnect and end at the Gulf Coast Booster Station.
This segment of the regional integrated loop system will boost regional resiliency, bidirectional water transfer capability and lays the groundwork for the southern regional loop with future pipeline projects.
Project Location
Hillsborough Boulevard from Yorkshire St. to US 41Latest Updates
The right-of-way has been cleared on Hillsborough Blvd. from Serris Dr. to Atwater St.
Materials are being procured and delivered.
Budget
Phase | Cost |
---|---|
Construction | $5,045110.89 |
Total Budget | $5,045110.89 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 03/04/2024 |
Project Phase
Construction
Last Updated
03/04/2024
Project Manager
Mike Martindell
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Design Engineer/Architect
Kimley Horn
Construction Contractor
Woodruff & Sons