Project Description
This project will install an 8-inch water main along Hillsborough Boulevard from Yorkshire St. to US 41. The water main will be installed parallel to the Peace River Manasota Water Authority’s 42-inch Phase 2B Pipeline.
The Peace River Manasota Water Authority’s Regional Integrated Loop Phase 2B Pipeline is a 42-inch steel potable water transmission main that will start at the Authority's existing 42-inch Regional Interconnect. The main will be installed along Hillsborough Blvd. to Chancellor Blvd. to Campbell St., then under the Myakka River to connect to the Gulf Coast Booster Station.
This segment of the regional integrated loop system will boost regional resiliency, bidirectional water transfer capability and lays the groundwork for the southern regional loop with future pipeline projects.
Project Location
Hillsborough Boulevard from Yorkshire St. to US 41Project Impacts
Evaro Drive and Eva Street at the Hillsborough Blvd. intersection will be closed starting at Tuesday, March 25. Detour signs will be in place to aid in travel through this area. Travelers are encouraged to choose an alternate route when possible.Latest Updates
Construction has begun.
Crews have installed the 42-inch and 8-inch pipe from Serris Drive to Overbrook Street. Once the pipe has been installed, they will begin restoring the site.
Budget
Phase | Cost |
---|---|
Construction | $5,045110.89 |
Total Budget | $5,045110.89 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 03/04/2024 |
Supporting Materials

Project Phase
Construction
Last Updated
03/24/2025
Project Manager
Mike Martindell
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Design Engineer/Architect
Kimley Horn
Construction Contractor
Woodruff & Sons