Project Description
This project installs an eight-inch water main along Hillsborough Boulevard from Yorkshire Street to U.S. 41. The water main will be installed parallel to the Peace River Manasota Water Authority’s 42-inch Phase 2B Pipeline.
The Peace River Manasota Water Authority’s Regional Integrated Loop Phase 2B Pipeline is a 42-inch steel potable water transmission main that will start at the Authority's existing 42-inch Regional Interconnect. The main will be installed along Hillsborough Boulevard to Chancellor Boulevard to Campbell Street, then under the Myakka River to connect to the Gulf Coast Booster Station.
This segment of the regional integrated loop system will boost regional resiliency, bidirectional water transfer capability and lays the groundwork for the southern regional loop with future pipeline projects.
Project Location
Hillsborough Boulevard from Yorkshire Street to U.S. 41.Latest Updates
- Installation of Charlotte County's eight-inch main is complete.
- Construction of Peace River’s 42-inch main continues south toward the Myakka River.
- Underwater installation of the 42-inch is tentative for September.
Budget
| Phase | Cost |
|---|---|
| Construction | $5,045,110.89 |
| Total Budget | $5,045,110.89 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 03/04/2024 |
Supporting Materials
Project Phase
Construction
Last Updated
07/02/2026
Project Manager
Mike Martindell
Public Relations
Stuart Gooden
Email Public Relations
Sponsor Department
Utilities
Design Engineer/Architect
Kimley Horn
Construction Contractor
Woodruff & Sons


