Project Description
Replacing all streetlights along Indian Trail Dr and Springwater Dr.Project Location
INDIAN TRAIL DR/ SPRINGWATER DR
Remove and replace all HPS streetlights with new solar lights and poles. The light poles being replaced are 40 years old.
Project Impacts
Improve overall lighting in the area located behind WAWA. Replace 39-year-old light poles.Latest Updates
Poles are on order waiting for arrival.
3/26/26 Poles and Fixtures have arrived. scheduling work with contractor.
4/29/26 Work is slated to begin the first week of May.
5/18/26 work has been pushed back to the first week of June.
6/1/26 work to be complete by 6/30/26
7/23/26 Job Complete
Budget
| Phase | Cost |
|---|---|
| Construction | $187,770.70 |
| Total Budget | $187,770.70 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 03/02/2026 | 06/30/2026 | 07/23/2026 |
Project Phase
Completed
Sponsor Department
Public Works Lighting District
Design Engineer/Architect
FLT
Construction Contractor
Charlotte County Public Works Lighting District


