Project Description
Project Location
350 East Marion Ave., Punta Gorda
Latest Updates
Project is complete.Budget
Phase | Cost |
---|---|
Design | $1,975,000 |
Construction | $16,565,000 |
Other Costs | $960,000 |
Total Budget | $19,500,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 04/01/2014 | 02/23/2015 | 02/21/2017 |
Design Development | 03/10/2016 | 08/03/2018 | 08/06/2018 |
Construction | 08/07/2018 | 02/22/2021 | 02/22/2021 |
Turnover & Closeout | 02/23/2021 | 03/09/2021 | 03/18/2021 |
Project Phase
Project Complete
Last Updated
11/05/2021
Project Manager
Jenny Buccieri
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Facilities Construction and Maintenance
Design Engineer/Architect
Sweet Sparkman Architects
Construction Contractor
Ajax Building Company, LLC