Project Description
The intent of this project is to harden the intersection from future storms. This includes replacing the existing span wire traffic signals with mast arm signalization and improve streetlights. Other improvements include milling and resurfacing the intersection pavement with new signing and marking and updated pedestrian crossings.
Project Location
The roadway intersection of Kings highway and Harborview road in Port Charlotte.Project Impacts
Improved traffic safety.Latest Updates
Adrew Site Work was awarded this project as the prime contractor. Notice to proceed date for construction was 8-25-25.
Completed work: ASW installed silt fence after stakeout was completed. Installation of post mount MOT (Maintenance of Traffic) signs was completed. Contractor performed soft digs to locate underground utilities, and there are some conflicts.
Upcoming work: Coordination with utility companies like CenturyLink for example to relocate cables that are in the way of the drill shafts foundations. Drill Shaft construction currently scheduled for early December.
Note: Mast arms for traffic signals have been ordered and are currently expected 5 1/2 months out. Current est. expected delivery 2-6-26 - 2-20-26.
Budget
| Phase | Cost |
|---|---|
| Engineering | $148,214.00 |
| Construction | $1,435,486.95 |
| Total Budget | $1,583,700.95 |
Lighting Department CIP Fund - Deisgn.
FDOT Grant- Construction.
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 02/13/2024 | 12/02/2024 | |
| Construction | 08/25/2025 | 03/07/2026 |
Project Phase
Construction
Last Updated
12/02/2025
Project Manager
Zach Patchell
Public Relations
Zach Patchell
Email Public Relations
Project Number
202500062
Sponsor Department
Public Work Engineering
Design Engineer/Architect
FTE
Construction Contractor
Andrew Site Wotrk


