Project Description
The intent of this project is to harden the intersection from future storms. This includes replacing the existing span wire traffic signals with mast arm signalization and improve streetlights. Other improvements include milling and resurfacing the intersection pavement with new signing and marking and updated pedestrian crossings.
Project Location
The roadway intersection of Kings Highway and Harborview Road in Port Charlotte.Project Impacts
Improved traffic safety.Latest Updates
Andrew Site Work was awarded this project as the prime contractor. Notice to proceed date for construction was 8-25-25.
*** On 3-30-26 a dump truck traveling through the intersection with the truck bed up hit the newly installed mast arm crossing Harborview Rd severely damaging it. This incident will greatly increase the completion date of this project. Mast arms have a 4 - 6-month lead time on manufacturing and delivery. *** Currently project staff is working on creating a change order with the assumed amount of contract days needed to be added to this project to cover this work. The contractor is said to be finalizing this request before submitting it for review.
Completed work - ASW and Sub-contractors have poured all four drill shaft foundations and have since installed three mast arms and signal heads. Additional recent work includes installation of signalization directional bores, pedestrian crossing bases, underground conduit and pull boxes.
Recent development - The fourth and final drill shaft was formed and poured on the SE corner. Currently the project awaits the curing of that shaft and passing concrete tests before scheduling the installation of the mast arm.
Upcoming work: ASW is planning the installation of mast arm 1-2 on the SE corner once passing concrete tests are received. This work is anticipated to begin towards the middle of August.
Budget
| Phase | Cost |
|---|---|
| Engineering | $148,214.00 |
| Construction | $1,435,486.95 |
| Total Budget | $1,583,700.95 |
Lighting Department CIP Fund - Deisgn.
FDOT Grant- Construction.
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 02/13/2024 | 12/02/2024 | |
| Construction | 08/25/2025 | 12/21/2026 |
Supporting Materials
Project Phase
Construction
Last Updated
07/31/2026
Project Number
202500062
Sponsor Department
Public Work Engineering
Design Engineer/Architect
FTE
Construction Contractor
Andrew Site Wotrk


