Project Description
The intent of this project is to harden the intersection from future storms. This includes replacing the existing span wire traffic signals with mast arm signalization and improve streetlights. Other improvements include milling and resurfacing the intersection pavement with new signing and marking and updated pedestrian crossings.
Project Location
The roadway intersection of Kings highway and Harborview road in Port Charlotte.Project Impacts
Improved traffic safety.Latest Updates
The construction preconstruction meeting was just held and a "notice to proceed date" was agreed on. Construction time will officially start on 8-25-25. Currently the contractor Andrew Site Work has been submitting shop drawing and submittals to the county project management for review and approval. Once approved materials will start to be ordered for the project.
Budget
| Phase | Cost |
|---|---|
| Engineering | $148,214.00 |
| Construction | $1,435,486.95 |
| Total Budget | $1,583700.95 |
Lighting Department CIP Fund - Deisgn.
FDOT Grant- Construction.
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 02/13/2024 | 12/02/2024 | |
| Construction | 08/25/2025 | 03/07/2026 |
Project Phase
Construction
Last Updated
08/05/2025
Project Manager
Zach Patchell
Public Relations
Zach Patchell
Email Public Relations
Project Number
20250062
Sponsor Department
Public Work Engineering
Design Engineer/Architect
FTE
Construction Contractor
Andrew Site Wotrk


