Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Loveland Grand Master Lift Station and 48-inch Gravity Interceptor

Project Description

Utility crews are constructing a master lift station and a major 48-inch wastewater gravity interceptor to transfer wastewater to the East Port Water Reclamation Facility (WRF). This project will improve the operation and efficiency of a substantial number of lift stations in the mid-county area. 

Project Location

Loveland Boulevard from Midas Court to Old Landfill Road and at the East Port Water Reclamation Facility. 

Project Impacts

Deficiencies in numerous sewer structures after installation has caused a delay in the project completion. The contactor is currently rectifying the deficiencies and is on schedule for completion by fall 2021.

Latest Updates

Crews are currently testing the system. 

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Construction 08/01/2018 11/30/2021

Supporting Materials

Project Phase
Construction

Last Updated
09/13/2021

Project Manager
Dean Campbell

Public Relations
Caroline Wannall
Email Public Relations

Sponsor Department
Utilities

Design Engineer/Architect
Johnson Engineering

Construction Contractor
Kiewit Infrastructure South Co.

Delivering Exceptional Service

Questions? Issues?

Contact Us