Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Loveland Grand Master Lift Station and 48-inch Gravity Interceptor

Project Description

Utility crews are constructing a master lift station and a major 48-inch wastewater gravity interceptor to transfer wastewater to the East Port Water Reclamation Facility (WRF). This project will improve the operation and efficiency of a substantial number of lift stations in the mid-county area. 

Project Location

Loveland Boulevard from Midas Court to Old Landfill Road and at the East Port Water Reclamation Facility. 

Project Impacts

Deficiencies in numerous sewer structures after installation has caused a delay in the project completion. The contactor is currently rectifying the deficiencies and is on schedule for completion by the end of 2021.

Due to the heavy flows of wastewater dumping into the new 48” line, odors have been detected in the area of Midway Blvd. The volume of wastewater routed into the main is stirring up waste and odors are being pushed out through the manholes. We have sealed manholes to help prevent the odors from escaping in the residential areas. We are working on a long term solution of chemical injection.

Latest Updates

Crews are currently testing the system and working on final items.

Loveland Boulevard road construction is completed.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Construction 08/01/2018 12/31/2021
Turnover & Closeout 01/01/2022 03/08/2022 03/10/2022

Supporting Materials

Loveland Grand Master Lift Station and 48-inch Gravity Interceptor Project Image

Project Phase
Project Complete

Last Updated
03/10/2022

Project Manager
Dean Campbell

Public Relations
Caroline Wannall
Email Public Relations

Sponsor Department
Utilities

Design Engineer/Architect
Johnson Engineering

Construction Contractor
Kiewit Infrastructure South Co.

Delivering Exceptional Service

Questions? Issues?

Contact Us