Project Description
Design and construct a pathway on Marathon Boulevard.Project Location
Marathon Boulevard from Gasparilla Road (CR771) to the Cape Haze Trail crossing.Latest Updates
This project is being joined with the Sunset Blvd. E. Sidewalk project for construction.
The contractor has received final completion and the project was closed out.
Budget
Phase | Cost |
---|---|
Design | $43,295.00 |
Construction | $166,750.00 |
Total Budget | $210,045.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/14/2021 | 11/30/2021 | |
Design Development | 02/02/2022 | 12/03/2022 | |
Construction | 08/02/2023 | 01/29/2024 | 02/28/2024 |
Turnover & Closeout | 01/15/2024 | 02/29/2024 | 03/22/2024 |
Project Phase
Project Complete
Last Updated
04/14/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD