Project Description
McGuire Park Phase II will complete Phase II of the McGuire Parks Master Plan. Amenities will include additional picnic pavilions, extended parking area, architectural fencing and community center.Project Location
21125 McGuire Avenue
Port Charlotte, Florida 33952
Project Impacts
Protected species mitigation
Inclement weather
Equipment and material supply chain delays
Latest Updates
In negotiations with proposed design firm.Budget
Phase | Cost |
---|---|
Design | $348,000.00 |
Construction | $2,552,000.00 |
Total Budget | $2,900,000.00 |
Capital Projects Fund
Impact Fees
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 09/30/2025 | 02/04/2026 | |
Construction | 02/04/2026 | 12/31/2026 | |
Turnover & Closeout | 12/31/2026 | 01/31/2027 |

Project Phase
Planning and Project Approval
Last Updated
09/22/2025
Project Manager
Vicki Chichura
Public Relations
Brian Gleason
Email Public Relations
Project Number
c722201
Sponsor Department