Project Description
The Mid-County Library was heavily damaged from Hurricane Ian. We continue working to establish the requirements to repair the facility through standard critical path processes, design and repair the facility to its pre-storm condition, and taking the opportunity to make improvements where applicable.Project Location
Mid-County Regional Library
2050 Forrest Nelson Blvd.
Port Charlotte, Florida 33952
Project Impacts
Lead times for equipment, supply chain delays
Insurance review timelines
Inclement weather
Revisions to updated codes
Latest Updates
Pre-Design meeting held 1/16/2024
Kick-off meeting held in March 2024
Reviewing project designs
Early work packages under development
Signed and Sealed Drawings Received 8/14/24
Construction Manager at Risk have submitted plans for permitting
Temporary fencing installed between sidewalk and canal for safety after Hurricanes Helene and Milton casued additional damages
Budget
Phase | Cost |
---|---|
Design | $693,327.00 |
Construction | $3,869,224.45 |
Total Budget | $4,562,551.45 |
Hurricane Fund
Insurance Reimbursements
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/16/2024 | 10/25/2024 | |
Construction | 10/01/2024 | 03/30/2026 | |
Turnover & Closeout | 03/30/2026 | 04/30/2026 |
Project Phase
Construction
Last Updated
12/12/2024
Project Manager
Vicki Chichura
Public Relations
Brian Gleason
Email Public Relations
Project Number
d221001
Sponsor Department
Community Services
Design Engineer/Architect
CSA/CCM/ADG/AFK
Construction Contractor
Wharton Smith