Project Description
The Mid-County Library was heavily damaged from Hurricane Ian. We continue working to establish the requirements to repair the facility through standard critical path processes, design and repair the facility to its pre-storm condition, and taking the opportunity to make improvements where applicable.Project Location
Mid-County Regional Library
2050 Forrest Nelson Blvd.
Port Charlotte, Florida 33952
Project Impacts
Lead times for materials and equipment, supply chain delays
Insurance review timelines
Inclement weather.
Revisions necessary to bring any work up to code.
Latest Updates
The library building's exterior has been sealed, painted and its roof replaced.
Currently we are making progress within the library to restore the building back to its pre-hurricane condition.
Budget
Phase | Cost |
---|---|
Design | $693,327 |
Construction | $6,914,843 |
Total Budget | $7,608,170 |
Hurricane Fund
Insurance Reimbursements
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/16/2024 | 10/25/2024 | |
Construction | 10/01/2024 | 03/30/2026 | |
Turnover & Closeout | 03/30/2026 | 04/30/2026 |
Project Phase
Construction
Last Updated
07/14/2025
Project Manager
Vicki Chichura
Public Relations
Brian Gleason
Email Public Relations
Project Number
d221001
Sponsor Department
Community Services
Design Engineer/Architect
CSA/CCM/ADG/AFK
Construction Contractor
Wharton Smith