Project Description
Hurricane Ian damaged this bridge, we have to modify our existing design contract to include storm-related repairs.
The Midway Bridge over North Spring Lake (#014073) requires engineering services to provide minor rehabilitation and maintenance to the bridge structure.
Project Location
The bridge is located on Midway Boulevard just southwest of US 41 over North Spring Lake.Latest Updates
Upcoming Project Activities - January 2026
The Midway Bridge Rehabilitation project is currently underway and is scheduled for completion in February 2026.
The contractor is in the process of installing the revetment system to repair the damaged slope beneath the bridge. The contractor is working on the pile jacket repairs under the bridge.
Budget
| Phase | Cost |
|---|---|
| Design | $88,735.05 |
| Construction | $983,435 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 10/07/2021 | 09/09/2022 | |
| Construction | 10/13/2025 | 02/10/2026 |
Project Phase
Construction
Last Updated
01/15/2026
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Project Number
2021002053
Sponsor Department
Public Works
Design Engineer/Architect
HDR
Construction Contractor
Thomas Marine Construction