Project Description
Design and construct a 6' sidewalk with a pedestrian bridge on the west side of Midway Boulevard from US 41 to Lakeview Boulevard as part of Safe Routes to Schools (HB41).Project Location
West side of Midway Boulevard from the US41 intersection South to Lakeview BoulevardLatest Updates
100% plans complete, Project is on hold as Charlotte County Utilities designs their septic to sewer conversion in this area so work can be done at the same time to minimize impact to the area.Budget
Phase | Cost |
---|---|
Design | $199,845.00 |
Construction | $2,484,230.00 |
Total Budget | $2,684075.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 09/13/2018 | 11/01/2019 | 10/13/2020 |
Project Phase
Planning and Project Approval
Last Updated
12/04/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD