Project Description
These 2 bridges currently require design services to implement the FDOT maintenance and repair items for each of the respective bridges.
Bridge #014044 Chamberlain Boulevard over Jupiter Waterway.
Bridge #014045 Chamberlain Boulevard over Apollo Waterway.
Project Location
Bridge #014044 Chamberlain Boulevard over Jupiter Waterway.
Bridge #014045 Chamberlain Boulevard over Apollo Waterway.
Latest Updates
Project Activities for December 2025
The County has received the 100% design plans and construction documents. Once the signed and sealed plans are in hand, we will forward the complete package to the Purchasing Department to initiate the construction bidding process.
Budget
| Phase | Cost |
|---|---|
| Design | $197,560 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 01/29/2024 | 10/03/2025 |
Project Phase
Design Development
Last Updated
12/02/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Project Number
2024001656
Sponsor Department
Public Works
Design Engineer/Architect
DRMP Engineering