Project Description
The Chamberlain Bridge over the Cheshire Waterway, originally constructed in 1970, is scheduled for repairs to extend its lifespan and ensure continued safe use. This project includes procuring an engineering firm to design the necessary repairs, followed by contracting with a construction firm to carry out the rehabilitation work.Project Location
Chamberlain Boulevard over the Cheshire Waterway Bridge (#014046)Latest Updates
Project Activity - June 2026
Centro Consulting Group has been selected, and our initial scope and fee negotiation is scheduled for June 4, 2026. Once negotiations are complete, the design firm will provide a detailed schedule outlining the project’s design timeline.
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 07/10/2026 |
Project Phase
Design Development
Last Updated
06/05/2026
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Centro Consulting Group