Project Description
This project incorporates the design and construction of new turn lanes and traffic signal modifications at the intersection of Peachland Boulevard and Harbor Boulevard. New dedicated left turn lanes will be added to all four sections of the intersection along with signal modifications, sidewalks, and pedestrian crosswalk improvements.
Project Location
Intersection of Peachland Boulevard and Harbor Boulevard.Latest Updates
The design survey has started. 60% plans are due for review in early March 2026.
Budget
| Phase | Cost |
|---|---|
| Design | $344,825 |
| Construction | $1,750,000 |
| Total Budget | $2,094,825.00 |
Gas Tax C411620
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 02/11/2019 | 08/14/2019 | 08/14/2019 |
| Design Development | 09/02/2020 | 02/20/2026 |
Supporting Materials
Project Phase
Design Development
Last Updated
03/02/2026
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
19-279
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Florida Transportation Engineering
Construction Contractor
TBD