Project Description
This project incorporates the design and construction of new turn lanes and traffic signal modifications at the intersection of Peachland Boulevard and Harbor Boulevard. New left and right turn lanes will be added along with signal modifications, sidewalks, and pedestrian crosswalk improvements.
Project Location
Intersection of Peachland Boulevard and Harbor Boulevard.Latest Updates
Design survey has started. 60% plans are due for review on December 13, 2024
Budget
Phase | Cost |
---|---|
Design | $344,825 |
Construction | $1,750,000 |
Total Budget | $2,094,825 |
Gas Tax C411620
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 02/11/2019 | 08/14/2019 | 08/14/2019 |
Design Development | 09/02/2020 | 02/14/2025 |
Supporting Materials
Project Phase
Design Development
Last Updated
10/28/2024
Project Manager
Jeff Keyser
Public Relations
Kenna Hubai
Email Public Relations
Project Number
19-279
Sponsor Department
Public Works
Design Engineer/Architect
Florida Transportation Engineering
Construction Contractor
TBD