Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Pirate Harbor Maintenance Dredge - Exterior

Project Description

Since the last maintenance dredge of a portion of the Pirate Harbor access channel in 2019 new concerns for a need of dredging were brought to the county’s attention. This project will pick up just east of where the last maintenance dredge event left off in the access channel and will continue east into the connector channels. The interior finger canals don't require dredging.

Most, if not all, of this project falls outside or west of the government meander line and is considered aquatic preserve, which means this work is not covered at large by the county wide maintenance dredge exemptions that are in place.

Project Schedule:  Shall be completeted after discussions with Coastal Engineering Consultants.

Project Budget:  Shall be updated after review of the latest survey and discussions with the Advisory Committee at its next meeting on August 13, 2025.

Project Location

Portions of the Pirate Harbor access entrance channel and connector canals with the waterway system.

Project Impacts

Improved and safer navigation

Latest Updates

Coastal Engineering Consultants and county staff has finally received the Army Corps Dredge Permit required to move forward with the planned dredge project. CEC also finalized the post Ian bathymetric survey work and submitted an assessment to county staff reporting minimal impacts caused by the storm. Those impacts are too insignificant to be worth application to FEMA. County project management reported those results to the MSBU waterway advisory board and they recommended moving forward with a revised dredge project to fit within budget.

Update on July 22, 2025:  Coastal Engineering Consultants completed field work for the latest survey during the week of May 12.  Public works awaits the draft copy.  A report shall be prepared for submitting a claim to FEMA if sufficiently shoaling has occured to justify the effort.  Plans for dredging will also be prepared. 

Update on August 15, 2025:  A new schedule for the Design Development, Construction and Closeout Phases, respectively, shall be completed after discussions with Coastal Engineering Consultants. The Advisory Committee has requested that bids for dredging be opened in October-November 2025.  Looking at combining under one dredging contract with Alligator Creek dredging project.

Budget

Phase Cost
Engineering $137,690
Construction $To be Determined
Total Budget $To be Determined
Funding source(s): Pirate Harbor MSBU.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 03/10/2021 08/31/2025
Pirate Harbor Maintenance Dredge - Exterior Project Image

Project Phase
Design Development

Last Updated
08/15/2025

Project Manager
DeWayne Nodine

Public Relations
Chad Ray
Email Public Relations

Project Number
CMD2202.310.00000

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Coastal Engineering Consultants, Inc.

Construction Contractor
TBD

Delivering Exceptional Service

Questions? Issues?

Contact Us