Project Description
Design and construct a sidewalk on Quesada Avenue from Cochran Boulevard to Forrest Nelson Boulevard. Design and construct pedestrian signals at the intersection of Quesada Avenue and Forrest Nelson Boulevard.Project Location
North side of Quesada Avenue from Cochran Boulevard to Forrest Nelson Boulevard.Latest Updates
The contractor has installed the storm structures and pipes, stabilized base and concrete sidewalk is being installed at this time. Charlotte County Utility has completed a sewer main relocation at the Crestview Waterway to allow the installition of a barrier wall and is being installed now. The pedestrain signals have arrived for the Forrest Nelson intersection and are being installed now. A change order has been issued to the contract 55 days to allow for the delay of the pedestrain signals.Budget
Phase | Cost |
---|---|
Design | $133,681.00 |
Construction | $455,225.00 |
Total Budget | $588,906.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/31/2022 | 03/01/2023 | 07/31/2023 |
Construction | 10/21/2024 | 03/20/2025 |
Project Phase
Construction
Last Updated
04/14/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD