Project Description
Design and construct a sidewalk on Quesada Avenue from Cochran Boulevard to Forrest Nelson Boulevard. Design and construct pedestrian signals at the intersection of Quesada Avenue and Forrest Nelson Boulevard.Project Location
North side of Quesada Avenue from Cochran Boulevard to Forrest Nelson Boulevard.Latest Updates
The project is nearing completion a change order is being issued to add 45 days to the contract from a delay on the repair of a damaged FPL line. The roadway has been repaved and opened to traffic. Waiting on the handrail to be installed over the Lion Heart Waterway. FPL will be installing street lighting at the corner of Quesada and Forrest Nelson and then the pedestrain signals will be turned on.Budget
Phase | Cost |
---|---|
Design | $133,681.00 |
Construction | $455,225.00 |
Total Budget | $588,906.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/31/2022 | 03/01/2023 | 07/31/2023 |
Construction | 10/21/2024 | 03/20/2025 |
Project Phase
Construction
Last Updated
07/02/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD