Project Description
Design and construct a sidewalk on Quesada Avenue from Cochran Boulevard to Forrest Nelson Boulevard. Design and construct pedestrian signals at the intersection of Quesada Avenue and Forrest Nelson Boulevard.Project Location
North side of Quesada Avenue from Cochran Boulevard to Forrest Nelson Boulevard.Latest Updates
The 90 % plans were received and are under review by staff. They are working on the area of sidewalk going over the Crestview waterway to fit the sidewalk in the tight area.Budget
Phase | Cost |
---|---|
Design | $133,681.00 |
Construction | $455,225.00 |
Total Budget | $588,906.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/31/2022 | 03/01/2023 |
Project Phase
Design Development
Last Updated
09/19/2023
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD