Project Description

The Board of County Commissioners has requested a sidewalk be designed and constructed on Rampart Blvd. as part of the 2020 Sales Tax CIP

Project Location

Rampart Blvd. from Luther Rd. to Rio De Janeiro Ave.

Latest Updates

The 30% planes were reviewed and comments were sent back to the EOR to address and work on the 60% plans

Budget

Phase Cost
Design $174,930.00
Funding source(s): This project is part of the 2020 Sales tax CIP

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 12/01/2022 02/12/2023 02/01/2023
Design Development 02/01/2023 06/30/2025
Construction 11/03/2025 09/01/2026

Project Phase
Design Development

Last Updated
06/09/2025

Project Manager
Raymond Slade

Public Relations
Chad Ray
Email Public Relations

Project Number
c412104

Sponsor Department
Public Works

Design Engineer/Architect
TBD

Construction Contractor
TBD

Sales Tax Project

Delivering Exceptional Service

Questions? Issues?

Contact Us