Project Description
The Deep Creek Street & Drainage MSBU has requested a sidewalk be designed and constructed on Rampart Blvd.Project Location
Rampart Blvd. from Rio DeJaneiro Ave. to Navigator Rd. and Rampart Blvd. to 1457 San Cristobal Ave.Latest Updates
Scope has been approved we are working on a design fee at this time.Budget
Phase | Cost |
---|---|
Design | $64,000.00 |
Construction | $308,000.00 |
Total Budget | $372,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 12/01/2022 | 01/16/2023 | |
Design Development | 02/01/2023 | 01/23/2024 |
Project Phase
Planning and Project Approval
Last Updated
03/13/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c412204
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD