Project Description
The Deep Creek Street & Drainage MSBU has requested a sidewalk be designed and constructed on Rampart Blvd.Project Location
Rampart Blvd. from Rio De Janeiro Ave. to Navigator Rd. and Rampart Blvd. to 1457 San Cristobal Ave.Latest Updates
The 30% plans were received and are under review by staff for comments. Review comments will be sent back to the Engineer to address and work on the 60% plans will start.Budget
Phase | Cost |
---|---|
Design | $64,000.00 |
Construction | $308,000.00 |
Total Budget | $372,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 12/01/2022 | 01/16/2023 | |
Design Development | 02/01/2023 | 06/30/2025 | |
Construction | 11/03/2025 | 09/01/2026 |
Project Phase
Design Development
Last Updated
04/29/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412204
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor