Project Description
The Board of County Commissioners has requested a sidewalk be designed and constructed on Rampart Boulevard as part of the 2020 Sales Tax CIPProject Location
Rampart Boulevard from Luther Road to Rio De Janeiro Avenue.Latest Updates
The consultant is finalizing the 90% design plans, which are being developed in conjunction with Sales Tax Phases 1 and 3. The consultant is also coordinating with FDOT on the I-75 overpass segment.Budget
| Phase | Cost |
|---|---|
| Design | $174,930.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 12/01/2022 | 02/12/2023 | 02/01/2023 |
| Design Development | 02/01/2023 | 01/31/2026 | |
| Construction | 04/03/2026 | 09/01/2027 |
Project Phase
Design Development
Last Updated
01/13/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412104
Sponsor Department
Public Works Engineering
Design Engineer/Architect
DRMP Inc.
Construction Contractor
TBD