Project Description
The Board of County Commissioners has requested a sidewalk be designed and constructed on Rampart Boulevard as part of the 2020 Sales Tax CIPProject Location
Rampart Boulevard from Luther Road to Rio De Janeiro Avenue.Latest Updates
The 30% planes were reviewed and comments were sent back to the EOR to address and work on the 60% plansBudget
| Phase | Cost |
|---|---|
| Design | $174,930.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 12/01/2022 | 02/12/2023 | 02/01/2023 |
| Design Development | 02/01/2023 | 10/31/2025 | |
| Construction | 11/03/2025 | 09/01/2026 |
Project Phase
Design Development
Last Updated
08/12/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412104
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD