Project Description
The Deep Creek Street & Drainage MSBU has requested a sidewalk be designed and constructed on Rampart Boulevard.Project Location
Rampart Boulevard from Rio De Janeiro Avenue to Navigator Road and Rampart Boulevard to 1457 San Cristobal Avenue.Latest Updates
-
The consultant is finalizing the 90% design plans, which are being developed in coordination with Sales Tax Phases 1 and 2.
-
The consultant is coordinating with FDOT regarding the I-75 overpass segment.
Budget
| Phase | Cost |
|---|---|
| Design | $64,000.00 |
| Construction | $308,000.00 |
| Total Budget | $372,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 12/01/2022 | 01/16/2023 | |
| Design Development | 02/01/2023 | 05/04/2026 | |
| Construction | 05/04/2026 | 03/31/2027 |
Project Phase
Design Development
Last Updated
03/02/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412204
Sponsor Department
Public Works Engineering
Design Engineer/Architect
DRMP Inc.
Construction Contractor
TBD