Project Description
The Deep Creek Street & Drainage MSBU has requested a sidewalk be designed and constructed on Rampart Boulevard.Project Location
Rampart Boulevard from Rio De Janeiro Avenue to Navigator Road and Rampart Boulevard to 1457 San Cristobal Avenue.Latest Updates
The 30% plans were reviewed and comments were sent back to the EOR to address and work on the 60% plans will start.Budget
| Phase | Cost |
|---|---|
| Design | $64,000.00 |
| Construction | $308,000.00 |
| Total Budget | $372,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 12/01/2022 | 01/16/2023 | |
| Design Development | 02/01/2023 | 10/31/2025 | |
| Construction | 11/03/2025 | 09/01/2026 |
Project Phase
Design Development
Last Updated
08/12/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
c412204
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD