Riverside Boat Ramp Replacement

Project Description

Design the replacement of the existing Riverside Boat Ramp to include boarding pier.

Project Location

8120 Riverside Dr, Punta Gorda, FL 33982

Project Impacts

US Army Corps of Engineers

Weather

Florida Department of Environmental Protection

Fish & Wildlife Conservation

Latest Updates

The project began on January 5, 2026.  Riverside Park will be closed through April, 2026.

Because this boat ramp is going to be formed and poured concrete, it requires a coffer dam to allow the concrete to cure in a dry environment for a specified amount of time.  Turbidity barriers are also required to minimize particulates entering the marine environment during the construction process.  To date, the turbidity barriers have been installed.  The coffer dam has been errected.  The area within the coffer dam has been drained.

Next steps include removing the old boat ramp and excavating the earth to allow the concrete forms to be installed and concrete to be poured.

Check back for future updates in approximately 2 weeks!

Budget

Phase Cost
Design $80,000
Construction $2,000,000
Total Budget $2,080,000.00
Funding source(s): Capital Projects

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 08/04/2021 10/29/2021 11/30/2021
Design Development 02/18/2022 12/29/2023 02/03/2025
Construction 01/05/2026 07/31/2026
Turnover & Closeout 08/07/2026 09/07/2026
Riverside Boat Ramp Replacement Project Image

Project Phase
Construction

Last Updated
01/21/2026

Project Manager
Robb Green

Public Relations
Brian Gleason
Email Public Relations

Project Number
pm21001

Sponsor Department
Community Services

Design Engineer/Architect
Weiler Engineering Corporation

Construction Contractor
Thomas Marine Construction