Project Description
Design the replacement of the existing ramp to include boarding pier(s)Project Location
8120 Riverside Dr, Punta Gorda, FL 33982Project Impacts
US Army Corps of EngineersLatest Updates
We are still waiting on Florida Fish and Wildlife Conservation to complete review of plans for Riverside.
Budget
Phase | Cost |
---|---|
Design | $80,000 |
Construction | $2,000,000 |
Total Budget | $2,080,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 08/04/2021 | 10/29/2021 | |
Design Development | 02/18/2022 | 04/17/2023 | |
Construction | 08/31/2023 | 08/30/2024 | |
Turnover & Closeout | 09/28/2024 | 10/30/2024 |

Project Phase
Planning and Project Approval
Last Updated
03/31/2023
Project Manager
Pedro Agosto
Public Relations
Brian Gleason
Email Public Relations
Project Number
pm21001
Sponsor Department
Community Services
Design Engineer/Architect
Weiler Engineering Corporation
Construction Contractor
TBD