Project Description
Design and construct the replacement of the existing Riverside Boat Ramp to include boarding pier.
Project Location
8120 Riverside Dr, Punta Gorda, FL 33982Project Impacts
US Army Corps of Engineers
Weather
Florida Department of Environmental Protection
Fish & Wildlife Conservation
Latest Updates
The Riverside Park boat ramp replacement was completed May 8, 2026 and the park reopened May 9, 2026. Thank you to all of our Riverside neighbors for your patience and understanding as we made these improvements. Thank you to Weiler Engineering (now APEX) for an excellent design. Thank you to Thomas Marine Construction for a well-run project and a well-build structure. And last but not least thank you to the Charlotte County Board of County Commissioners for funding a project that benefits every water sports enthusiast in Charlotte County ... though our Riverside neighbors may want to keep it their little secret. ; )
Budget
| Phase | Cost |
|---|---|
| Design | $80,000 |
| Construction | $2,000,000 |
| Total Budget | $2,080,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 08/04/2021 | 10/29/2021 | 11/30/2021 |
| Design Development | 02/18/2022 | 12/29/2023 | 02/03/2025 |
| Construction | 01/05/2026 | 07/31/2026 | |
| Turnover & Closeout | 08/07/2026 | 09/07/2026 |
Project Phase
Construction
Last Updated
05/07/2026
Project Manager
Robb Green
Public Relations
Brian Gleason
Email Public Relations
Project Number
pm21001
Sponsor Department
Community Services
Design Engineer/Architect
Weiler Engineering Corporation
Construction Contractor