Project Description
Design and construct the replacement of the existing Riverside Boat Ramp to include boarding pier.
Project Location
8120 Riverside Dr, Punta Gorda, FL 33982Project Impacts
US Army Corps of Engineers
Weather
Florida Department of Environmental Protection
Fish & Wildlife Conservation
Latest Updates
The project began on January 5, 2026. Riverside Park will be closed through April, 2026.
The underwater structure of the new boat ramp has been completed! We now move on to installing the docks and completing all of the upgrades above the water line and on dry land. The project is on time, on budget, and remains on track for completion in April.
Budget
| Phase | Cost |
|---|---|
| Design | $80,000 |
| Construction | $2,000,000 |
| Total Budget | $2,080,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 08/04/2021 | 10/29/2021 | 11/30/2021 |
| Design Development | 02/18/2022 | 12/29/2023 | 02/03/2025 |
| Construction | 01/05/2026 | 07/31/2026 | |
| Turnover & Closeout | 08/07/2026 | 09/07/2026 |
Project Phase
Construction
Last Updated
03/09/2026
Project Manager
Robb Green
Public Relations
Brian Gleason
Email Public Relations
Project Number
pm21001
Sponsor Department
Community Services
Design Engineer/Architect
Weiler Engineering Corporation
Construction Contractor
Thomas Marine Construction