Project Description
Bridge 014113 Rotonda Blvd over Rotonda River was severely damaged during Hurricane Ian and is closed to all traffic, both vehicular and pedestrian. This project is for the design of permanent repairs or replacement to restore the bridge to service.
Project Location
Rotonda Blvd. over Rotonda River - Bridge #014113Latest Updates
Upcoming Project Activities - May 2025
The county hired an engineering firm to design a replacement bridge. That design is nearing completion.
The County has also hired outside counsel to appeal FEMA’s decision to not fund hurricane damage on bridge 014113. Staff is working closely with the group and will provide additional information when we have more to share.
Budget
Phase | Cost |
---|---|
Design | $323,790 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 06/16/2023 |
Supporting Materials
Project Phase
Planning and Project Approval
Last Updated
06/12/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
KCI Engineers