Rotonda Bridge Rehabilitations Design #1 - Bridges 014111

Project Description

Rotonda West MSBU has 17 bridges needing design services to implement the FDOT maintenance and repair items for each of the respective bridges.

Due to Hurricane Ian, bridge #014113 sustained substantial damage and was closed to all traffic, we had to remove this bridge from the current RLI design contract.  Bridge #014113 will need to be rehabilitated or replaced, we currently have a separtate design contract for this bridge. 

The deisgn for bridge #014111 is complete but ON HOLD until after bridge #014113 has been designed and construction is completed.

Rotonda Circle over White Marsh Creek South - Bridge #014111

Project Location

Rotonda Circle over White Marsh Creek South - Bridge #014111

Rotonda Blvd. over Rotonda River - Bridge #014113

See attached location map.

Latest Updates

Currently this project is ON HOLD.

The design firm has completed the 100% design plans and technical specification for bridge #014111.  Staff has reviewed and approved plans.  The County is going to wait to put this project out for construction until bridge #014113 (suffered major damage from Hurricane Ian) has been repair due to traffic conflicts.      

Budget

Phase Cost
Design $131,150
Funding source(s): Rotonda West MSBU

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 01/24/2022 03/31/2022
Design Development 03/31/2022 06/16/2023

Supporting Materials

Project Phase
Design Development

Last Updated
09/06/2023

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Project Number
20220183

Sponsor Department
Public Works

Design Engineer/Architect
KCI