Project Description
Rotonda West MSBU has 17 bridges needing design services to implement the FDOT maintenance and repair items for each of the respective bridges.
This project is for construction for bridge rehabilitations -
Rotonda Circle over Oakland Hills Creek - Bridge #014060
Rotonda Circle over Rotonda Channel 32-1 - Bridge #014063
Rotonda Circle over Pinehurst Creek S - Bridge #014100
Rotonda Circle over Pinehurst Creek N - Bridge #014101
Rotonda Circle over Broadmoor Creek N - Bridge #014104
Rotonda Circle over Long Meadow Creek S - Bridge #014107
Project Location
Rotonda Circle over Oakland Hills Creek - Bridge #014060
Rotonda Circle over Rotonda Channel 32-1 - Bridge #014063
Rotonda Circle over Pinehurst Creek S - Bridge #014100
Rotonda Circle over Pinehurst Creek N - Bridge #014101
Rotonda Circle over Broadmoor Creek N - Bridge #014104
Rotonda Circle over Long Meadow Creek S - Bridge #014107
See Location Map.
Latest Updates
Upcoming Activities for June 2025
Rotonda Circle over Long Meadow Creek S. Bridge (#014107) is Complete.
Rotonda Circle over Broadmoor Creek N. Bridge (#014104) is Complete.
Construction will begin on June 2, 2025, at the Rotonda Circle over Pinehurst Creek S. (#014101) bridge. This bridge will be closed for 30 days.
Budget
Phase | Cost |
---|---|
Design | $149,020 |
Construction | $1,800,213.45 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 05/19/2023 | 04/12/2024 | |
Construction | 01/13/2025 | 08/11/2025 |
Supporting Materials
Project Phase
Construction
Last Updated
06/12/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
KCI Engineers
Construction Contractor
Thomas Marine Construction