Project Description
These 2 bridges currently require design services to implement the FDOT maintenance and repair items for each of the respective bridges.
Bridge #014105 is on Rotonda Circle over Broadmoor Creek South.
Bridge #014106 is on Rotonda Circle over Long Meadow Creek North.
Project Location
Bridge #014105 is on Rotonda Circle over Broadmoor Creek South.
Bridge #014106 is on Rotonda Circle over Long Meadow Creek North.
Latest Updates
Project Activities for June 2025
Villa Fuerte Construction will start construction on July 7, 2025.
Budget
Phase | Cost |
---|---|
Design | $114,785 |
Construction | $615,037.81 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 04/02/2024 | 09/27/2024 | |
Construction | 07/07/2025 | 10/06/2025 |
Project Phase
Construction
Last Updated
06/12/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Weiler Engineering Corp
Construction Contractor
Villa Fuerte Construction