Project Description
The project will replace the existing two-lane roadway on Sandhill Blvd from Kings Highway to Deep Creek Blvd, including intersection improvements at Capricorn Boulevard and Deep Creek Blvd. Possible relocations of existing Charlotte County and Peace River Manasota Regional Water Supply Authority utilities may be necessary.Project Location
Sandhill Blvd from Kings Highway to Deep Creek BlvdLatest Updates
30% construction plans are due for review on 6/03/2025.
Budget
Phase | Cost |
---|---|
Design | $1,658,000 |
Construction | $15,670,000 |
Total Budget | $17,328,000 |
Road Impact Fees
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/01/2023 | 02/12/2024 | 02/02/2024 |
Design Development | 07/18/2024 | 07/08/2026 | |
Construction | 10/05/2026 | 08/25/2028 |
Supporting Materials
Project Phase
Design Development
Last Updated
04/29/2025
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
c410914
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD