Project Description
The project will replace the existing two-lane Sandhill Blvd from Kings Highway to Deep Creek Blvd, including intersection improvements at Capricorn Blvd and Deep Creek Blvd. Possible relocations of existing Charlotte County and Peace River Manasota Regional Water Supply Authority utilities may be necessary.Project Location
Sandhill Blvd from Kings Highway to Deep Creek BlvdLatest Updates
The county is preparing an advertisement to obtain an engineering design firm to design the project.Budget
Phase | Cost |
---|---|
Design | $1,648,000 |
Construction | $14,728,000 |
Other Costs | $2,879,000 |
Total Budget | $19,255,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/01/2023 | 11/30/2023 | |
Design Development | 12/01/2023 | 06/30/2025 | |
Construction | 10/01/2025 | 10/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
11/27/2023
Project Manager
Jeff Keyser
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c410914
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD