Project Description
The project will replace the existing two-lane Sandhill Blvd from Kings Highway to Deep Creek Blvd, including intersection improvements at Capricorn Blvd and Deep Creek Blvd. Possible relocations of existing Charlotte County and Peace River Manasota Regional Water Supply Authority utilities may be necessary.Project Location
Sandhill Blvd from Kings Highway to Deep Creek BlvdLatest Updates
Johnson Engineering has submitted the design scope for county staff to review.Budget
Phase | Cost |
---|---|
Design | $1,658,000 |
Construction | $15,670,000 |
Total Budget | $17,328,000 |
Road Impact Fees
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/01/2023 | 02/12/2024 | 02/02/2024 |
Design Development | 02/27/2024 | 06/30/2025 | |
Construction | 10/01/2025 | 10/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
04/29/2024
Project Manager
Jeff Keyser
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c410914
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD