Project Description
The project will replace the existing two-lane roadway on Sandhill Boulevard from Kings Highway to Deep Creek Boulevard, including intersection improvements at Capricorn Boulevard and Deep Creek Boulevard. Possible relocations of existing Charlotte County and Peace River Manasota Regional Water Supply Authority utilities may be necessary.Project Location
Sandhill Boulevard from Kings Highway to Deep Creek Boulevard.Latest Updates
The 60% roadway construction plans have been reviewed by County staff, and comments have been returned to Johnson Engineering for review and revision.
Johnson Engineering is currently coordinating the 60% Charlotte County Utilities components and is also progressing with the right-of-way and proposed property sites for the stormwater pond locations.
Budget
| Phase | Cost |
|---|---|
| Design | $1,658,000 |
| Construction | $15,670,000 |
| Total Budget | $17,328,000.00 |
Road Impact Fees
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 10/01/2023 | 02/12/2024 | 02/02/2024 |
| Design Development | 07/18/2024 | 07/08/2026 | |
| Construction | 10/05/2026 | 08/25/2028 |
Supporting Materials
Project Phase
Design Development
Last Updated
04/01/2026
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
c410914
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD