Sandhill Boulevard Widening

Project Description

The project will replace the existing two-lane roadway on Sandhill Boulevard from Kings Highway to Deep Creek Boulevard, including intersection improvements at Capricorn Boulevard and Deep Creek Boulevard. Possible relocations of existing Charlotte County and Peace River Manasota Regional Water Supply Authority utilities may be necessary.  

Project Location

Sandhill Boulevard from Kings Highway to Deep Creek Boulevard.

Latest Updates

The 60% roadway construction plans have been reviewed by County staff, and comments have been returned to Johnson Engineering for review and revision.

Johnson Engineering is currently coordinating the 60% Charlotte County Utilities components and is also progressing with the right-of-way and proposed property sites for the stormwater pond locations.

Budget

Phase Cost
Design $1,658,000
Construction $15,670,000
Total Budget $17,328,000.00
Funding source(s):

Road Impact Fees

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 10/01/2023 02/12/2024 02/02/2024
Design Development 07/18/2024 07/08/2026
Construction 10/05/2026 08/25/2028

Supporting Materials

Sandhill Boulevard Widening Project Image

Project Phase
Design Development

Last Updated
04/01/2026

Project Manager
Jeff Keyser

Public Relations
Chad Ray
Email Public Relations

Project Number
c410914

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Johnson Engineering

Construction Contractor
TBD