Project Description
The main kitchen, laundry, and associated plumbing equipment has reached the end of it's useful life.With the recent addition of the Jail Imfirmary there is additional space that can now be repurposed. Project
renovates the jail's kitchen and laundry spaces while repurposing additional areas for Facilities and
jail operating inventory warehouse.
Project Location
28571 Airport Rd
Punta Gorda FL
Latest Updates
The shortlisting to select the design consultant was held January 30th and top-ranked firm will be presented at February 25th BOCC meeting for approvalBudget
| Phase | Cost |
|---|---|
| Design | $700,000 |
| Construction | $7,355,000 |
| Total Budget | $8,055,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 11/21/2025 | 02/25/2026 | 02/03/2026 |
| Design Development | 03/15/2026 | 11/30/2026 | |
| Construction | 12/30/2026 | 10/17/2027 | |
| Turnover & Closeout | 10/20/2027 | 11/17/2026 |
Project Phase
Planning and Project Approval
Last Updated
02/03/2026
Project Manager
Scott Brouillard
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Public Safety