South County Regional Park Playground Replacement

Project Description

Replacement of the existing playground equipment that has reached it's of life cycle. This will include the 5-12 and 2-5 ages play structures. The existing shade canopies will remain and be incorporated into the new equipment layout. Final design's from 3 vendors will be shared with the community so they can vote on the most liked concept. The design with the most votes is what will be installed.

Project Location

South County Rgional Park 

670 Cooper St.

Punta Gorda, FL 33950

Latest Updates

All desing concepts have been received. 

Survey will be ready to go live March 27 and will stay active for 14 days.

Budget

Phase Cost
Construction $500,000.00
Total Budget $500,000.00
Funding source(s): Capital Maintenance Projects- Playground Replacement

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 02/09/2026
Design Development 02/09/2026
Construction 08/17/2026
Turnover & Closeout 10/23/2026

Project Phase
Design Development

Last Updated
03/27/2026

Project Manager
Lacey Solomon