Project Description
South Gulf Cove MSBU FY24 has three (3) bridges needing design services to implement the FDOT maintenance and repair items for each of the respective bridges.
St. Paul Boulevard over Zephyr Waterway - Bridge #014065
San Domingo Boulevard over Santa Cruz Waterway - Bridge #014070
Ingraham Boulevard over Santa Cruz Waterway - Bridge #014072
Project Location
St. Paul Boulevard over Zephyr Waterway - Bridge #014065
San Domingo Boulevard over Santa Cruz Waterway - Bridge #014070
Ingraham Boulevard over Santa Cruz Waterway - Bridge #014072
Latest Updates
Upcoming Project Activities – April 2026
The contractor is continuing to submit technical submittals to the Engineer for review and approval. Once all required submittals, including the Maintenance of Traffic (MOT) plan and the project schedule, have been approved, we will be able to confirm the actual construction start date.
Budget
| Phase | Cost |
|---|---|
| Design | $128,960 |
| Construction | $1,195,628.70 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 03/29/2024 | 04/14/2025 | 05/06/2025 |
| Construction | 04/06/2026 | 08/04/2026 |
Project Phase
Construction
Last Updated
04/07/2026
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Project Number
2024001528
Sponsor Department
Public Works Engineering
Design Engineer/Architect
DRMP Engineering
Construction Contractor
Structural Technologies, LLC