Project Description
The project will replace two outdated and undersized buildings constructed in 1992 with a single, more efficient, up-to-date facility. The new facility will meet current safety and storm-resiliency standards and will accommodate increased staffing needs and future growth.Project Location
29751 Zemel Rd
Punta Gorda FL 33955
Project Impacts
This project is not expected to cause any disruption to landfill operations.Latest Updates
With the completion of the kickoff meeting, the team has officially begun the design phase. Potential building locations are currently being evaluated, and testing is underway to determine the most cost-effective and resilient site for the facility. Further updates will be provided as progress continues throughout the design process.
Budget
| Phase | Cost |
|---|---|
| Design | $588,801.00 |
| Construction | $6,233,000 |
| Other Costs | $130,000 |
| Total Budget | $6,681,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 09/18/2025 | 02/10/2026 | |
| Design Development | 04/01/2026 | 11/28/2026 | |
| Construction | 11/28/2026 | 08/25/2027 | |
| Turnover & Closeout | 08/25/2027 | 10/25/2027 |
Project Phase
Design Development
Last Updated
06/03/2026
Project Manager
Scott Brouillard
Public Relations
Brian Gleason
Email Public Relations
Project Number
C342601
Sponsor Department
Public Works
Design Engineer/Architect
ADG