Project Description
The county, in cooperation with FDOT District One, shall install landscaping in the median of SR 776.Project Location
SR 776 - Murdock Circle to Myakka River Bridge medians.Budget
Phase | Cost |
---|---|
Design | $69,300.00 |
Construction | $852,000.00 |
Total Budget | $921,300.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 04/17/2025 | 05/29/2026 | 04/23/2025 |
Construction | 07/01/2026 | 08/31/2026 | |
Turnover & Closeout | 08/23/2027 | 08/31/2027 |
Project Phase
Design Development
Last Updated
04/23/2025
Project Manager
Chuck Peters
Public Relations
Chad Ray
Email Public Relations
Project Number
25-209
Sponsor Department
Public Works
Design Engineer/Architect
Kimely-Horn