Project Description
The Charlotte County Erosion control Project includes providing erosion control and shoreline stabilization measures including beach nourishment, maintenance dredge bypassing, and stabilizing structures for approximately 5,000 linear feet of eroding gulf and inlet shorelines immediately adjacent to Stump Pass. The sand removed by the Maintenance Dreding of Stump Pass will be used to nourish the beaches north and south of the pass. The project limits for this activity will extend from Florida Department of Environmental Protection (FDEP) Reference Monument (R-Monument) R-18 south to R-21 on Manasota Key in the Stump Pass Beach State Park. The Project continues on Palm Island extending from approximately 1,200 feet northeast of R-22 along Stump Pass’ southern inlet shoreline and then along the gulf-front shoreline to approximately R-24.Project Location
The southern end of Manasota Key in the Stump Pass Beach State Park (900 Gulf Blvd, Englewood, FL 34223) and the northern shorline of Palm IslandLatest Updates
Pre-Construction Meeting held October 11, 2021.
Pumping on State Park began at 11:30 on December 20, 2021. Areas of active construction will closed to the public. To date the contractor has placed over 100,000 cubic yards on the State Park. The contractor has completed the sand placement and tilling on the State Park. They have mobilized to Don Pedro/Knight Island and resumed sand placement on March 4th. They have completed the dredging of Stump Pass and are currently demobilizing their equipment from the area. They anticipate all equipment removal, restoration of mob areas, and beach tilling to be complete by June 22.
Tentative Schedule for Project:
Mobilization: November 29- December 15 Complete
Dredge/Sand Placement on Stump Pass State Park: December 20 - March 1 Complete
Mobilize to Palm Island: March 1-3 Complete
Dredge/Sand Placement on Palm Island: March 4 - June 10 Complete
Demobilization: June 10- June 22
Budget
Phase | Cost |
---|---|
Design | $33,988 |
Construction | $2,196,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/04/2021 | 07/01/2021 | 07/01/2021 |
Construction | 11/29/2021 | 05/19/2022 |
Project Phase
Construction
Last Updated
06/15/2022
Project Manager
Matthew Logan
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Coastal Engineering Consultants
Construction Contractor
Atlantic and Gulf Dredging and Marine, LLC