Project Description
Design and construct a sidewalk on Sunset Boulevard East.Project Location
Sunset Boulevard East from Bermont Road to South Fairway DriveLatest Updates
This project is being joined with the Marathon Blvd. Pathway project for construction.
The work on Sunset Blvd. E. is complete with the contractor getting substantial completion as soon as work is completed on Marathon Blvd. this project will be closed out.
Budget
Phase | Cost |
---|---|
Design | $38,395.00 |
Construction | $148,350.00 |
Total Budget | $186,745.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/01/2021 | 11/30/2021 | 01/17/2022 |
Design Development | 02/02/2022 | 12/03/2022 | 02/28/2023 |
Construction | 07/17/2023 | 01/13/2024 |
Project Phase
Construction
Last Updated
10/17/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
Weiler Engineering
Construction Contractor
TBD