Project Description
Design and construct a sidewalk on Sunset Boulevard East.Project Location
Sunset Boulevard East from Bermont Road to South Fairway DriveLatest Updates
This project is being joined with the Marathon Blvd. Pathway project for construction. The contractor is starting on Marathon Blvd. first, doing survay and installing silt fence to get started. They will be installing the new watermain removing the old main and then installing the concrete pathway.
The work on Sunset Blvd. E. is complete with the contractor getting substantial completion they are now finishing up punch list item to complete the project.
Budget
Phase | Cost |
---|---|
Design | $38,395.00 |
Construction | $148,350.00 |
Total Budget | $186,745.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/01/2021 | 11/30/2021 | 01/17/2022 |
Design Development | 02/02/2022 | 12/03/2022 | 02/28/2023 |
Construction | 07/17/2023 | 01/13/2024 |
Project Phase
Construction
Last Updated
03/13/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
Weiler Engineering
Construction Contractor
TBD