Project Location
Relocate from current site residing in the south county on Airport Road Annex. New site selection is located centralized within the county providing efficient staff utilization during elections. Current warehouse location will conflict with new sheriff's district office and consolidated training operations in FY 20-21. Move will enable larger, modern space to accomodate climate controlled secure storage.Latest Updates
Construction Update:
Interior overhead doors were fully installed, except for the hoods and one exterior unit. A replacement barrel is on order for the remaining door, expected onsite within 10 days. Fire alarm wiring and notification device installation continued throughout the warehouse, along with ongoing data cabling and lighting terminations. The fire line and domestic water lines were pressure tested, with final inspections remaining. The domestic water line was connected to the building. Conduit for overhead door eye wires and controls ware installed and adjusted to accommodate the hoods.
Budget
Phase | Cost |
---|---|
Design | $395,340.00 |
Construction | $7,193,113.00 |
Total Budget | $8,200,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/20/2022 | 05/19/2023 | |
Construction | 05/03/2024 | 02/01/2026 |

Project Phase
Construction
Last Updated
06/12/2025
Public Relations
Brian Gleason
Email Public Relations
Project Number
c192104
Design Engineer/Architect
Grace Hebert Curtis Architects
Construction Contractor
Wharton-Smith
