Project Location
Relocate from current site residing in the south county on Airport Road Annex. New site selection is located centralized within the county providing efficient staff utilization during elections. Current warehouse location will conflict with new sheriff's district office and consolidated training operations in FY 20-21. Move will enable larger, modern space to accomodate climate controlled secure storage.Latest Updates
Construction Update:
Exterior and interior painting continues. Ductwork is being installed in the Mechanical Room. Toilets are being installed in the restrooms. Large fans in the Emergency Management area have been installed. Permanent lighting fixtures began being installed in storage areas, while miscellaneous lighting and junction boxes continued throughout the building. Drywall repairs have been completed in both the IT and changing rooms. Wiring continued to be pulled for low voltage and fire alarm systems. The Fire Pump Enclosure was lifted and set into place. Final grading and preparation for the first lift of pavement were completed on the south side of the building.
Budget
Phase | Cost |
---|---|
Design | $395,340.00 |
Total Budget | $4,700,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/20/2022 | 05/19/2023 | |
Construction | 05/03/2024 | 02/01/2026 |
Project Phase
Construction
Last Updated
04/30/2025
Public Relations
Brian Gleason
Email Public Relations
Project Number
c192104
Construction Contractor
Wharton Smith
