Project Location
Relocate from current site residing in the south county on Airport Road Annex. New site selection is located centralized within the county providing efficient staff utilization during elections. Current warehouse location will conflict with new sheriff's district office and consolidated training operations in FY 20-21. Move will enable larger, modern space to accomodate climate controlled secure storage.Latest Updates
Construction Update:
- All footings are complete.
- Form work for tilt panels has started, including installation of formliner and rebar.
- Stormwater Drainage installation has started, including roughly 150 linear feet of RCP (reinforced concrete pipe) in the ground, and the installation of structures.
- Elevator pit formwork in progress, including below grade waterproofing.
Budget
Phase | Cost |
---|---|
Design | $395,340.00 |
Total Budget | $4,700,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/20/2022 | 05/19/2023 | |
Construction | 05/03/2024 | 02/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
08/16/2024
Project Manager
Justin Dunn
Public Relations
Brian Gleason
Email Public Relations
Project Number
c192104
Construction Contractor
Wharton Smith